A HAZOP produces a list of actions. Months later, someone asks one of the hardest questions in process safety: how do you know that action was actually done? If the answer is "the tracker says Closed", you have a status, not evidence.
This post sets out what good close-out evidence looks like and how to record it so it still makes sense to an auditor, an inspector or your successor.
Why close-out evidence matters
UK law doesn't name HAZOP. What it does require is a suitable and sufficient assessment of risks, reviewed when there is reason to suspect it is no longer valid or when there has been a significant change (Management of Health and Safety at Work Regulations 1999, regulation 3). At establishments covered by COMAH, the operator must take all measures necessary to prevent major accidents and limit their consequences, and must be able to demonstrate that to the competent authority (COMAH Regulations 2015, regulation 5).
A HAZOP action is often one of those measures. If the team judged a safeguard inadequate, an unverified close-out leaves the gap open while the paperwork says it is shut, and a closed action with no evidence is hard to demonstrate to anyone.
"Complete" is not "Closed"
A simple discipline is to keep two separate states:
- Complete: the action owner says the work is done.
- Closed: someone other than the owner has checked the evidence and agrees the intent of the action has been met.
The gap between the two is where weak close-outs hide. Typical examples:
- The action asked for a high-level trip. The close-out says "trip installed", but nobody confirms it was proof-tested, added to the test schedule or written into the operating procedure.
- The action asked the team to "consider" something. The close-out says "considered, no action", with no record of who considered it, on what basis, or whether the HAZOP risk ranking still holds.Separating Complete from Closed in your tracker makes these cases visible.
What good evidence looks like
Good evidence answers four questions: what was done, where it can be seen, who checked it, and whether the original concern is resolved. In practice that means six things.
1. It is specific to the action. The evidence should match the wording of the action. If the action asked for a relief valve to be checked for the fire case, the evidence is the revised sizing calculation and the updated relief register, not a general note that "relief has been reviewed".
2. It is traceable. Give a document number and revision, a work order number, a drawing revision, a management of change (MOC) reference or a procedure version. A reader should be able to find the thing without having to ask you.
3. It shows the change is in place, not just designed. A design change needs proof that it was installed and commissioned: a completed work order, a pre-startup check, an as-built drawing. Physical changes usually go through the site's modification procedure (HSE's plant modification and change procedures guidance describes what one should cover), so the MOC record is often the best single piece of evidence.
4. It covers the knock-on documents. Ask what else should have changed: operating procedures, P&IDs, cause and effect charts, alarm and trip schedules, maintenance and test routines, training records. An action can be technically done and still leave operators working from the old procedure.
5. It is verified by someone independent of the owner. The verifier doesn't need to be senior. They need to be competent in the subject and not the person who did the work. Record their name, the date and what they looked at.
6. It closes the loop on risk. State whether the residual risk now matches what the HAZOP team intended. If the action was rejected or replaced by an alternative, record the reason and who accepted it. A rejected action is a legitimate outcome when it is justified and authorised; an undocumented one is not.
Weak evidence: common patterns
- "Done", "Complete", "See email" or an empty evidence field.
- A screenshot of a design with no sign it was built.
- An attachment that doesn't mention the equipment tag or the HAZOP node.
- A closure date earlier than the completion date of the work order.
- The action owner verifying their own action.
- A due date extended several times with no recorded reason and no interim measure.
None of these prove the work wasn't done. They mean the record can't show that it was.
How to record it in your tracker
A practical close-out record needs only a handful of fields:
- Action ID, HAZOP node and deviation, and the original action text, copied exactly rather than paraphrased.
- Owner, due date, and any agreed extension with its reason.
- Evidence description and reference (document number and revision, work order, MOC number).
- Knock-on documents updated (yes, no or not applicable, with references).
- Verifier name, date and comment.
- Status: Open, Complete (awaiting verification), Closed, or Rejected with justification.
Add overdue logic that counts days past the due date, and report Complete-but-not-Closed actions as their own number. That figure is often the most honest measure of how well your close-out process works, and tracked over time it makes a useful leading indicator.
A simple close-out routine
- The owner marks the action Complete and attaches or references the evidence.
- The verifier checks the evidence against the original action text, not a summary of it.
- The verifier checks that the knock-on documents have been updated.
- The verifier records the decision: Closed, or returned to the owner with a reason.
- Every so often, someone samples a few Closed actions and re-checks the evidence. At COMAH establishments, Schedule 2 expects the safety management system to address monitoring performance, including procedures for the ongoing assessment of compliance with the objectives of the major accident prevention policy and safety management system (COMAH Regulations 2015, Schedule 2). Sampling closed actions is a simple, practical way to do part of that.
Tools to help
- Free: the HAZOP Action Close-Out Checklist (PDF) is a one-page check to run before you mark any action Closed.
- Free: the HAZOP & MOC Action Close-Out Evidence Guide (PDF) gives examples of strong and weak evidence for common action types.
- The HAZOP Action Tracker Excel Template Pack separates Complete from Closed, flags overdue actions automatically, and includes a dashboard, a user guide and email templates for chasing action owners.
- If you manage both HAZOP and MOC actions, the Close-Out Bundle includes the HAZOP and MOC tracker packs plus the Evidence Guide.
Want occasional practical tips and new free templates? Join the HazardOps Safety tips list (about once a month, unsubscribe any time).
FAQ
Is HAZOP a legal requirement in the UK?
No regulation names HAZOP. The law requires a suitable and sufficient risk assessment and, at COMAH establishments, all measures necessary to prevent major accidents and limit their consequences. HAZOP is a widely used method for meeting those duties on process plant.
Who should verify a HAZOP action?
Someone competent in the subject who did not do the work. Depending on the site, that might be a process safety engineer, the HAZOP chair or a technical authority. Your site procedure should say who.
Can an action be closed without doing exactly what it said?
Yes, if an alternative is justified, the reason is recorded and someone with the right authority accepts it. Record it as rejected or closed by an alternative, never silently.
This article is generic guidance based on published UK legislation and HSE material. It is not legal advice and does not guarantee compliance. Adapt it to your site and have it reviewed by a competent person.