Every process plant sometimes needs to defeat a safeguard. A trip is inhibited to allow a start-up, a gas detector is overridden during calibration, an interlock is bypassed to clear a faulty signal. Each one opens a period when the plant runs with less protection than the design assumed.
The aim isn't to ban overrides. It is to make sure every one is justified, authorised, compensated, time-limited and removed, and that the record shows it.
Bypass, override, inhibit: agree the terms
Sites use these words differently. Your procedure should define them and cover every way a safeguard can be defeated, for example:
- software forces, overrides and inhibits in a control or safety system;
- key switches and maintenance override switches;
- jumpers, links and lifted wires;
- mechanical bypasses, such as an open bypass valve around a shutdown valve, or a locked-closed valve under a relief device;
- alarm shelving and suppression.
If it stops a safeguard doing its job, it belongs in the procedure, whatever the site calls it.
What UK law and HSE guidance say
The general duties apply. At COMAH establishments the operator must take all measures necessary to prevent major accidents and limit their consequences (COMAH Regulations 2015, regulation 5), and every employer must assess risks and review that assessment when things change (Management of Health and Safety at Work Regulations 1999, regulation 3). A defeated safeguard changes the risk, so it needs its own assessment.
HSE's COMAH technical guidance on control systems is more specific. It says logic systems "are likely to incorporate provisions for fault alarms and overrides, for which there should be suitable management control arrangements", and it lists override management as covering authorisation, security, recording, monitoring and review of overrides, and reset requirements. On alarms, the same page says controls should exist to make sure shelved or suppressed alarms are returned to an active state.
If your safeguards include safety instrumented functions, the functional safety standard BS EN 61511 also sets expectations for bypassing them. Check your site's safety instrumented system documentation alongside this post.
When an override becomes a change
A short, planned override carried out under an approved procedure, such as inhibiting one detector while it is calibrated, is a controlled operation. An override that will last longer than the procedure allows, or has no clear end, is effectively a temporary change and should go through your management of change (MOC) process.
Set the boundary in your procedure: the maximum duration before an override must be re-authorised, and the point at which it must become a temporary MOC.
Eight steps to control an override
1. Request. Who wants it, which safeguard (by tag), why, and how long it is expected to last.
2. Assess. What hazard does the safeguard protect against? What could happen while it is defeated? Which operating limits apply in the meantime? The depth of assessment should match the consequence.
3. Compensating measures. Decide what replaces the lost protection. Examples include continuous attendance at the equipment, manual readings at a defined interval, a reduced rate or inventory, a temporary alternative detector, or stopping certain activities nearby. Name the person responsible for each measure.
4. Authorise. Set authorisation levels by risk: the more significant the safeguard, the more senior and independent the approver. The person applying the override shouldn't be its only authoriser.
5. Identify. Label the field device or panel, and make sure the override is visible in the control room. Nobody should discover an override by accident.
6. Communicate. Record the override in the shift log and include it in every shift handover until it is removed.
7. Review the time limit. Each override gets an expiry date and time. If it is still needed, it must be re-authorised, not just left on. Overrides past their expiry should be escalated.
8. Remove and verify. Record when the safeguard was reinstated, by whom, and how it was confirmed to be working, including a function test where needed.
What to record in an inhibit register
A good register lets anyone answer "what is defeated on this plant right now?" in under a minute. Useful fields:
- Register number, equipment tag and a description of the safeguard.
- Type of defeat (software override, key switch, jumper, mechanical bypass, alarm shelving).
- Reason, and the linked permit to work or MOC number.
- Date and time applied, applied by, authorised by.
- Risk level and the compensating measures, with the person responsible for each.
- Expiry date and time, and any re-authorisations with reasons.
- Date and time removed, removed by, and how reinstatement was verified.
The summary view should show the active overrides, those past expiry, and the longest-standing ones.
Warning signs
- Overrides with no expiry date.
- Overrides active across many shifts without anyone re-authorising them.
- The same tag overridden again and again, which usually points to a faulty instrument or a design problem that needs a defect report or an MOC.
- Compensating measures written down but not actually in place.
- Overrides found during walk-rounds or system checks that aren't on the register.
- Alarm shelving with no automatic or procedural return to service.
Tools to help
- The Bypass / Override (Inhibit) Register Excel Template Pack records every bypass with its authorisation, compensating measures and planned end, flags overdue and long-duration bypasses, and builds a live shift handover list of everything that is active.
- Free: the MOC Close-Out Quick Check (PDF) helps when a long-running override has become a temporary change.
- Free: the Pre-Startup Safety Review (PSSR) Checklist (PDF) includes checks on safeguards and instruments before start-up, a useful moment to confirm nothing is still overridden.
- The Management of Change (MOC) Tracker Excel Template Pack tracks temporary changes with expiry dates and overdue flags, so long-running overrides handled as temporary changes don't drift.
Want occasional practical tips and new free templates? Join the HazardOps Safety tips list (about once a month, unsubscribe any time).
FAQ
Is alarm shelving the same as an override?
It defeats a protective function, so treat it the same way: authorise it, time-limit it and make sure the alarm returns to service. HSE's control systems guidance calls for controls that return shelved or suppressed alarms to an active state.
Who should authorise an override?
Someone competent and independent of the person applying it, at a level that matches the risk. Your procedure should set the levels.
How long can a trip stay inhibited?
There's no single legal figure. Your procedure should set a maximum, require re-authorisation to extend it, and require a temporary MOC beyond a defined limit.
Do we need a separate register if overrides are in the control system log?
A system log shows what changed, but not why, who authorised it or which compensating measures are in place. A register adds that context, and it can also cover mechanical bypasses that no control system records.
This article is generic guidance based on published UK legislation and HSE material. It is not legal advice and does not guarantee compliance. Adapt it to your site and have it reviewed by a competent person.