A management of change (MOC) system depends on two documents: the form someone fills in to propose a change, and the tracker that follows that change through to closure. If the form misses a question, the hazard review misses it too. If the tracker can't show which changes are stuck, temporary changes quietly become permanent.
This post sets out what a practical MOC form and tracker should contain, based on UK requirements and HSE guidance, with the common gaps to watch for.
What the law and HSE guidance say
At COMAH establishments, the safety management system must address the management of change, described in Schedule 2 as the adoption and implementation of "procedures for planning modifications to, or the design of new installations, processes or storage facilities" (COMAH Regulations 2015, Schedule 2).
For every employer, the risk assessment must be reviewed if there has been a significant change in the matters it relates to (Management of Health and Safety at Work Regulations 1999, regulation 3). An MOC process is the usual way of making sure that review happens before the change, not after.
HSE's technical guidance on plant modification and change procedures says a form of risk assessment should identify the hazards the change creates, and that proposals should be formally authorised by competent people after a technical review. HSE also notes that organisational change is usually not analysed and controlled as thoroughly as plant or process change.
First, define what counts as a change
Most MOC problems start with a change nobody recognised as a change. Your procedure should list the types that must go through MOC, for example:
- Plant and equipment: new, modified or removed items, including piping, relief devices and instruments.
- Process conditions: operating limits, set points, flow rates, inventories.
- Chemicals: new raw materials, suppliers, grades or concentrations.
- Control and safety systems: logic, trip settings, alarm settings, software versions.
- Procedures: operating, maintenance and emergency procedures.
- Organisation: roles, staffing levels, shift patterns, contractors taking over work.
- Temporary changes, which need the same review as permanent ones plus an expiry date.
Also define "replacement in kind" (like-for-like): an item that meets the same specification and needs no MOC. Write the definition down, because "like-for-like" is one of the most loosely used phrases on any site.
What to include in the MOC form
A good form walks the originator and reviewers through the change in a fixed order. These are the sections worth having.
1. Identification. A unique MOC number, a short title, the area or unit, equipment tags, the originator and the date.
2. Description and reason. What is changing, why, and what happens if the change isn't made. Attach sketches or marked-up drawings.
3. Type and duration. Permanent, temporary (with an expiry date and a removal or conversion plan) or emergency (with a retrospective review date).
4. Hazard review. Which method was used and why it is proportionate: a checklist for a simple change, what-if or HAZOP for a complex one. Record the findings and the reference to the full study.
5. Impact checklist. A yes, no or not applicable question for each item the change might affect: P&IDs and process flow diagrams, operating procedures, relief and blowdown, cause and effect charts, alarm and trip schedules, maintenance and inspection routines, training, emergency arrangements, permits to work, hazardous area classification, environmental permits and, where relevant, COMAH documents such as the safety report.
6. Actions arising. Each action with an owner and due date, marked as "before start-up" or "after start-up".
7. Approvals. The technical, operations and process safety reviewers and the final approver, with names and dates. The originator shouldn't be the final approver of their own change.
8. Pre-startup safety review (PSSR). Confirmation that the change was built as approved, before-start-up actions are complete, procedures are updated and people are trained before the plant is restarted or the change is brought into use.
9. Close-out. Confirmation that drawings and documents are updated, after-start-up actions are complete, and temporary changes have been removed or converted through a new MOC. Record who verified it and when.
What to include in the MOC tracker
The form records one change. The tracker shows the whole system. Useful fields:
- MOC number, title, area and type (permanent, temporary, emergency).
- Originator and MOC owner.
- Current stage: Proposed, Under review, Approved, Implemented, PSSR complete, In use, Close-out pending, Closed.
- Key dates: raised, approved, PSSR, in use, closed.
- Temporary change expiry date.
- Number of open actions, split into before and after start-up.
- Overdue flags and days open.
The reports that matter most are short:
- Temporary changes past their expiry date.
- Changes in use but not closed, and how long they have been in that state.
- Changes with open before-start-up actions that are already marked as in use. There shouldn't be any.
Common gaps
- Temporary changes that become permanent by default because nobody tracked the expiry date.
- Changes in use for months while drawings and procedures still show the old design.
- Reviewers approving changes they originated.
- Organisational changes handled outside the MOC system.
- Emergency changes that never get their retrospective review.
- "Like-for-like" used to skip review for items that aren't.
Linking MOC and PSSR
The PSSR is the last check before a change goes live. Keep it as a defined step in the MOC, with its own sign-off, rather than an informal walk-round. The free checklist below gives you a starting structure.
Tools to help
- Free: the MOC Close-Out Quick Check (PDF) is a short check to run before you close a change.
- Free: the Pre-Startup Safety Review (PSSR) Checklist (PDF) covers design, procedures, training, safeguards, relief and isolation, drawings and outstanding actions before start-up.
- The Management of Change (MOC) Tracker Excel Template Pack tracks each change from proposal to closure, with overdue logic, a dashboard, a user guide and email templates for chasing owners.
Want occasional practical tips and new free templates? Join the HazardOps Safety tips list (about once a month, unsubscribe any time).
FAQ
Is management of change a legal requirement in the UK?
At COMAH establishments the safety management system must address the management of change (Schedule 2). For all employers, risk assessments must be reviewed after a significant change (MHSWR regulation 3). An MOC procedure is the usual way to show both happen.
Does a like-for-like replacement need an MOC?
Not if it is a true replacement in kind that meets the same specification. Define the term in your procedure, and when in doubt, raise an MOC.
How long can a temporary change stay in place?
Your procedure should set a maximum and require re-approval through MOC to extend it. The tracker should flag any temporary change past its expiry date.
Do organisational changes need an MOC?
HSE guidance highlights organisational change as an area that is often not controlled as well as plant change. It is good practice to route significant organisational changes through MOC, or through a parallel process with its own review and approval.
This article is generic guidance based on published UK legislation and HSE material. It is not legal advice and does not guarantee compliance. Adapt it to your site and have it reviewed by a competent person.