ITP E-016 LV Cabling and Terminations - Inspection and Test Plan Template with Worked Example (Excel, UK, 2026)
A complete inspection and test plan for LV Cabling and Terminations: a blank template and a fully worked example, written the way a Tier 1 quality reviewer expects to receive it.
The worked example separates installation checks from Part 6 testing so that the sign-off sequence matches BS 7671: inspect first, then test, then certify.
What is in the workbook: a Read Me First sheet, the blank Template and the Worked Example with 19 inspection lines (5 hold points), each with the activity, the acceptance criterion, the reference (BS 5467, BS 6121-1:2005, BS 6724, BS 7211, BS 7671, BS EN 61008-1, BS EN 61009-1, BS EN 62444), the inspection level (H/W/S/R), the record produced and three-party sign-off columns.
Points specific to this activity:
- Every test result is recorded against the calibrated instrument that produced it. An uncalibrated tester invalidates the certificate.
- Insulation resistance minimums are from BS 7671 Table 64 (Regulation 643.3.2). Do not quote a table number from a superseded edition.
- Terminations are a hold point at the board and a surveillance item at accessories - the risk is not the same.
Part of the StructAssure ITP Starter Pack (M&E) - buy the full library to get every ITP at a lower price per document, or the Complete Site Quality System for everything. Every standard is cited at the edition written into the document and checked against the current edition at the time of build; your project specification takes precedence over the standards cited.
What you get with every StructAssure document: 12 months email support, free updates when a standard it cites changes, and if it is not as described we will put it right or refund you.
Format: one Microsoft Excel workbook (.xlsx), A4 landscape, branded, unlocked and editable. Single-company licence included.
Built by StructAssure Ltd - Chartered construction and quality professionals (MCIOB, CQP MCQI, MAPM).